Description

Date: 28/07/2012 To: 03/08/2012

Block Paving Lift and relay

 

West Kirkby - Wirral - Merseyside

 

This project is to lift  incorrectly installed block paving, lower levels by excavating ground a further 150mm than normal as existing block paving has been laid too high above the damp course. This will result in the finished level being lowered. We are also going to retain the rear garden with solid oak sleepers and install a lineal drainage system where the block paving will be sloping away from the house into the lineal drain.

 

 